TB 9-2320-280-35-12
Section XIV. COMPUTER STAND CABLE INSTALLATION
14-1. Assemble and install front cable carrier (11) on shelf (1) with two screws (9), nuts (8), and
screws (7).
14-2. Route Ethernet cable (6) along bottom of shelf (1) to front cable carrier (11).
14-3. Assemble and install rear cable carrier (10) on shelf (1) with two screws (9), nuts (8), and screws (7).
14-4. Route PCMCIA cable (5) along bottom of shelf (1) to rear cable carrier (10) and secure
PCMCIA cable (5) to shelf (1) using screw (3) and clamp (4).
14-5. Route DC-DC cable (2) along bottom of shelf (1) to rear cable carrier (10) and secure DC-DC cable (2)
to shelf (1) using screw (3) and clamp (4).
14-6. Route Parallel cable (13) along bottom of shelf (1) to rear cable carrier (10) and secure
Parallel cable (13) to shelf (1) using existing screw (12) and clamp (4).
4
3
2
5
1
6
~
7
8
4
13
12
9
11
10
7.
SCREW 93195A1113 QTY. 4
2. DC-DC POWER ADAPTER CABLE
8.
NUT 90675A005 QTY. 4
P/O PA1540-647 QTY. 1
9.
SCREW MS51959-15 QTY. 4
3. SCREW MS35207-263 QTY. 2
10.
CABLE CARRIER 55835K44 QTY. 1
4. LOOP CLAMP 3225T43 QTY. 3
5. PCMCIA CABLE A3265957 QTY. 1
11.
CABLE CARRIER 55835K42 QTY. 1
6. ETHERNET CABLE A3265597 QTY. 1
13.
PARALLEL CABLE P/O A3265640 QTY. 1
Figure 5-29.