SERVICE UPON RECEIPT AND INSTALLATION
Section I. SERVICE UPON RECEIPT OF EQUIPMENT
c. Check to see whether the equipment has been
changed by a modification work order (MWO ). If
When packed for shipment, the test set, test
the equipment has been modified, the MWO
adapter, and technical manual are inclosed together
number will appear on the front panel. If modified,
in a corrugated cardboard box. No special
s e e t h a t a n y o p e r a t i o n a l i n s t r u c t i o n changes
procedures are required for unpacking.
resulting from the modification have been entered
2-2. Checking Unpacked Equipment
in the equipment manual. Check also to see
a. Inspect the test set for damage incurred
whether all MWO'S current at the time the
during shipment. If the test set has been damaged,
equipment is placed in use have been applied.
report the dam age on DD Form 6.
NOTE
b. Check to see that the test set is complete, as
Current MWO'S applicable to the
listed on the packing slip. If a packing slip is not
e q u i p m e n t are listed in DA Pam 310-7.
a v a i l a b l e , check the contents against table 1-2.
R e p o r t all discrepancies in accordance with TM
38-750.
Section II. INSTALLATION INSTRUCTIONS
without any battery connected to the test
set.
The TS-2530/UR is a hand-carried test equip-
Perform a preliminary operational check on the TS-
m e n t , packaged and shipped with Battery Test
2530 / UR as follows:
Adapter MX-8801 / PRC-90 as a complete unit
a. Obtain an unused, fresh battery BA-1568/ U
with all parts and components installed. Therefore,
f r o m Radio Set AN/ PRC-90.
no tools, materials, or installation instructions are
b. O b t a i n a n o p e r a b l e T S - 2 5 3 0 / U R a n d
required.
B a t t e r y Test Adapter MX-8801 / PRC-90.
2-4. Initial Checking and Adjustment of
NOTE
Equipment
If possible, retain a TS-2530 / UR, MX-
NOTE
8801 / PRC-90. and BA-1568 / U for the
Adjusting the TS-2530 / UR is limited to
AN / PRC-90 as a maintenance standard.
t h e meter zero adjustment. Use a non-
c. Perform the appropriate operating procedures
metallic screwdriver to adjust meter zero,